TE School District Submits VFMS Fencing Permit Application … Tredyffrin Township Denies Request!

No FencingValley Forge Middle School fencing was not on the Tredyffrin Township Board of Supervisors April 20th meeting, but many Chesterbrook residents attended the meeting and spoke against the TE School Board’s project. The supervisors deferred all questions/comments to the township’s solicitor Vince Donohue for response who told audience members that the township would not get involved until the District made either a “permit request or there was a shovel in the ground”. Chesterbrook residents left the meeting hoping for a more proactive approach by township officials.

The ‘wait and see’ township attitude was quickly tested when the School District submitted a permit request for the Valley Forge Middle School fencing this past week. The township’s Planning and Zoning Director Matt Bauman denied the permit request on the spot and in a letter to the School District, stated

“Please be advised that the permit is hereby denied. The issuance of the permit would violate the terms of that certain Zoning Hearing Board Decision in Appeal Number 64-02 issued December 17, 2002.”

The School Board’s action attempted to violate the legal agreement between TESD and the Chesterbrook Civic Association. Without an amendment to the Special Exception granted by Tredyffrin Township’s Zoning Hearing Board in 2002, how does the School Board think that they can move forward with their planned fencing project at VFMS?

Unless something has changed in the last couple of days, there has been no movement on part of the School Board or the District to resolve the VFMS fencing situation directly with the Green Hills residents or with the Chesterbrook Civic Association. As David Miller, president of CCA told us at the supervisors meeting, there has been no return of phone calls or emails to either himself or to the Green Hills and CCA attorneys from the School Board or their attorney David Falcone of Saul Ewing. Yet the District went ahead and made a permit application for the fencing!

I encourage Chesterbrook residents and Valley Forge Road neighbors to bring their chain link fencing opposition message to the TE School Board meeting on Monday, April 27, 7:30 PM at Conestoga High School. At some point, the School Board has to listen to those that they were elected to serve.

Security fencing for Valley Forge Middle School, TE Middle School and Conestoga High School – TE School District seeks variance to construct 6-foot fence

fencing 1During 2014, 5-foot high chain link fencing was installed around TESD’s five elementary schools – Beaumont, New Eagle, Valley Forge, Hillside and Devon. Sandy Hook and other school shootings pushed the issue of school security into the limelight and the elementary school fencing project was one of the security upgrades recommended by the District’s Safety Committee.

The construction of the elementary school security fencing project was not without controversy. Residents opposed the District’s decision to fence the elementary school for a variety of reasons. Some suggested that the fencing would make it more difficult for children to evacuate in emergencies — concern that they could become trapped inside the property by the fencing and that the fencing could slow emergency aid. Others cited inconvenience; aesthetics and monetary cost (approximately $220K) in their opposition to the fencing and some questioned if the District obtained the required building permits. In the end, the elementary schools received their security fencing last year.

Apparently, the District’s fencing project was not contained to the elementary schools. A surprise to some, security fencing is planned for Valley Forge Middle School, TE Middle School and Conestoga High School. At the October 27, 2014 TE School Board meeting, the school board approved Daley & Jalboot’s 2015 infrastructure implementation fee proposal on the consent agenda. Included in the architect’s project was Project #1405, the installation of perimeter site fencing at the three schools. Daley & Jalboot’s fee is $$8,600 and they estimate the construction costs at $236K.

The security-fencing project of the middle schools and high school is out for bid and construction is set to start June 24 with completion by the start of school in September.

Unlike the elementary school fencing project in 2014, the District has a hurdle to get over before they can move forward. The District’s plan to construct a 6-foot chain link fence at Valley Forge Middle School and TE Middle School requires a variance from the Zoning Hearing Board. Tredyffrin Township’s Zoning Hearing Board will hear these two appeals tonight at 7 PM and residents are encouraged to attend and provide comments.

The proposed chain link fencing at Valley Forge Middle School may be a challenge for the Zoning Hearing Board. The school is in Chesterbrook, a planned community of 28 villages, and each of the villages is independently managed by homeowners associations and governed by specific bylaws. The Chesterbrook village of Green Hills (single family homes) is adjacent to Valley Forge Middle School. The plan for VFMS fencing is along Valley Forge Road and on the shared property line with Green Hills. Because the proposed chain link fencing is not consistent with the homeowner association bylaws of Green Hills, and an earlier agreement between these homeowners and the school board regarding development, the approval for the variance may not be a given for the school district.